2 ramps set to ease traffic near Paseo/I-25 construction

Created: 05/20/2014 1:25 PM
By: Nikki Ibarra, KOB Eyewitness News 4

The New Mexico Department of Transportation says construction is moving along on schedule for the Paseo del Norte/I-25 Interchange project. 

In about a week, the new San Antonio off-ramp--coming off I-25 North--will open.

On Tuesday, construction crews were working on putting up light poles near the off-ramp which goes over the new San Mateo on-ramp. The on-ramp is set to open in about two weeks.

"What we did is we took the ramp and moved it south so that we would have a longer merge distance not so close to San Antonio. Then, we're taking the new on-ramp from San Mateo and the frontage road will go underneath it and come onto I-25. All that has moved away from Paseo," Gallegos said.

The new off-ramp will be 1,800 feet south of the ramp drivers are using now. That ramp will be closed once the new San Antonio off-ramp opens.

NMDOT hopes to have the entire construction project done and open by December.


KOB welcomes a lively and courteous discussion as long as you follow the rules of conduct set forth in our Terms of Use. Comments are not pre-screened before they post. You agree that anything you post may be used, along with your name and profile picture, in accordance with our Privacy Policy and the license you have granted pursuant to our Terms of Use.