Carlsbad Caverns: More time needed for elevator repairs

The Associated Press
May 23, 2018 10:31 PM

CARLSBAD, N.M. (AP) - The primary elevators at Carlsbad Caverns National Park will not be working by Memorial Day despite plans to have renovations done ahead of the holiday weekend.

Advertisement

Park officials said Wednesday that completion of the work has been pushed back to June 15. The contractor was working 10-hour days, seven days a week in an effort to finish by May 25 but more time was needed.

The primary elevator system was originally installed in 1955 and went out of service in November 2015 when a motor shaft sheared off. Work to repair and modernize the elevators began last December.

Republican Congressman and gubernatorial candidate Steve Pearce says he's disappointed in the continued delay given the park's role in drawing visitors to southeastern New Mexico.

Credits

The Associated Press

Copyright 2018 The Associated Press. All rights reserved.

Advertisement
Comment on Facebook

Share 4 - News Tips - Photos - Videos
  Share a News Tip, Story Idea, Photo, Video



Advertisement

Relay Media Amp

Advertisement

Advertisement







DA to charge stepmother in death of 5-year-old boy


Rio Rancho boy shaves his head in tribute to cancer-fighting classmate

Man in critical condition following shooting near UNM

State lawmaker accused of DWI expected in court